New LNG Export Facilities starting up soon - Jan 30
Posted: Tue Jan 30, 2024 4:41 pm
Notes below are from my friends that work over at AEGIS Hedging Solutions.
Golden Pass is estimated to be commercial in-service July 2024-July 2025, although the developer has announced that mechanical completion is expected in 2H 2024, with first LNG in early 2025.
Plaquemines LNG is expected to start between March 2025 and September 2026, with likely an extended commissioning timeline.
Corpus Christi Stage 3 is hopeful that first LNG from the trains can be produced in 2024 (faster-than-anticipated). However, commercial operations for start-ups are projected between June 2026 and Dec 2027.
Notes above are from S&P, but as we look across vendors, there is some disparity and different guesswork each accounts for, so timelines can differ.
-------------------
The "noise" coming out of the Biden Administration about not approving new LNG export facilities is political BS. The three facilities above are fully approved and should start increasing natural gas demand in 9-12 months. Keep in mind that these facilities are MASSIVE construction projects and delays are common, especially when everything needs to be tested.
America has a significant trade deficit. Exporting LNG is needed to help solve that serious problem.
Golden Pass is estimated to be commercial in-service July 2024-July 2025, although the developer has announced that mechanical completion is expected in 2H 2024, with first LNG in early 2025.
Plaquemines LNG is expected to start between March 2025 and September 2026, with likely an extended commissioning timeline.
Corpus Christi Stage 3 is hopeful that first LNG from the trains can be produced in 2024 (faster-than-anticipated). However, commercial operations for start-ups are projected between June 2026 and Dec 2027.
Notes above are from S&P, but as we look across vendors, there is some disparity and different guesswork each accounts for, so timelines can differ.
-------------------
The "noise" coming out of the Biden Administration about not approving new LNG export facilities is political BS. The three facilities above are fully approved and should start increasing natural gas demand in 9-12 months. Keep in mind that these facilities are MASSIVE construction projects and delays are common, especially when everything needs to be tested.
America has a significant trade deficit. Exporting LNG is needed to help solve that serious problem.