New Natural Gas Pipeline in the Permian Basin
Posted: Tue Sep 10, 2024 11:27 am
From EIA website: https://www.eia.gov/todayinenergy/detail.php?id=63044
Natural gas pipeline takeaway capacity in the Permian Basin will soon increase as the Matterhorn Express Pipeline, with a capacity of 2.5 billion cubic feet per day (Bcf/d), is expected to begin service this month, according to EnLink Midstream, one of the project’s stakeholders.
Matterhorn (a joint venture with Whitewater, EnLink Midstream, Devon Energy, and MPLX) will transport natural gas from the Permian Basin to Katy near Houston, Texas. Natural gas production from the Permian Basin—primarily associated gas from growing oil production operations—has more than doubled since 2018, reducing regional spot natural gas prices and prompting greater demand for new pipeline takeaway capacity to transport natural gas to more viable markets.
In addition to Matterhorn, three new Permian Basin pipeline projects with a combined capacity of 7.3 Bcf/d have been approved and are in various stages of development:
> Apex Pipeline, with a capacity of 2.0 Bcf/d, is designed to transport natural gas from the Permian Basin to Port Arthur, Texas. Operator Targa Resources expects the pipeline to enter service in 2026.
> Blackcomb Pipeline, with a capacity of 2.5 Bcf/d, is designed to transport natural gas from the Permian Basin to Agua Dulce in south Texas. Operator Whitewater Midstream expects the pipeline to enter service in 2026.
> Saguaro Connector Pipeline, with a capacity of 2.8 Bcf/d, is designed to transport natural gas from the Permian Basin to the U.S.-Mexico border. We expect the pipeline, which connects with the Sierra Madre pipeline on the Mexico side, to enter service by 2027–28.
Pipeline operators have also announced other projects with a total capacity of 7.0 Bcf/d designed to transport natural gas from the Permian Basin to demand centers in Mexico and along the Texas Gulf Coast. These projects, if realized, could come into service between 2025 and 2028. < Per Antero Resources recent presentation the first new pipeline into Mexico will be online mid-2025 with capacity of 1.4 Bcf per day.
Natural gas pipeline takeaway capacity in the Permian Basin will soon increase as the Matterhorn Express Pipeline, with a capacity of 2.5 billion cubic feet per day (Bcf/d), is expected to begin service this month, according to EnLink Midstream, one of the project’s stakeholders.
Matterhorn (a joint venture with Whitewater, EnLink Midstream, Devon Energy, and MPLX) will transport natural gas from the Permian Basin to Katy near Houston, Texas. Natural gas production from the Permian Basin—primarily associated gas from growing oil production operations—has more than doubled since 2018, reducing regional spot natural gas prices and prompting greater demand for new pipeline takeaway capacity to transport natural gas to more viable markets.
In addition to Matterhorn, three new Permian Basin pipeline projects with a combined capacity of 7.3 Bcf/d have been approved and are in various stages of development:
> Apex Pipeline, with a capacity of 2.0 Bcf/d, is designed to transport natural gas from the Permian Basin to Port Arthur, Texas. Operator Targa Resources expects the pipeline to enter service in 2026.
> Blackcomb Pipeline, with a capacity of 2.5 Bcf/d, is designed to transport natural gas from the Permian Basin to Agua Dulce in south Texas. Operator Whitewater Midstream expects the pipeline to enter service in 2026.
> Saguaro Connector Pipeline, with a capacity of 2.8 Bcf/d, is designed to transport natural gas from the Permian Basin to the U.S.-Mexico border. We expect the pipeline, which connects with the Sierra Madre pipeline on the Mexico side, to enter service by 2027–28.
Pipeline operators have also announced other projects with a total capacity of 7.0 Bcf/d designed to transport natural gas from the Permian Basin to demand centers in Mexico and along the Texas Gulf Coast. These projects, if realized, could come into service between 2025 and 2028. < Per Antero Resources recent presentation the first new pipeline into Mexico will be online mid-2025 with capacity of 1.4 Bcf per day.